Accelerating Da Nang key projects after stagnations triggered by COVID-19 crisis and harsh weather

0:00

Da Nang People’s Committee Vice Chairman Le Quang Nam on Wednesday morning paid inspection visits to the construction sites of the Hoa Lien Water Plant in Hoa Vang District and the traffic improvement project at the western end of the Tran Thi Ly Bridge. Vice Chairman Nam asked construction units to maintain a bustling working atmosphere and race against time to accelerate construction works after previous stagnations mainly triggered by the COVID-19 crisis and harsh weather conditions raging last year.

1 nghe b c3 a1o c c3 a1o ti e1 ba bfn c4 91 e1 bb 99 c c3 b4ng tr c3 acnh nh c3 a0 m c3 a1y n c6 b0 e1 bb 9bc h c3 b2a li c3 aan


Da Nang People’s Committee Vice Chairman Le Quang Nam (4th from right, 1st row)


inspecting the progress of the Hoa Lien Water Plant

Visiting the construction site of the Hoa Lien Water Plant, Vice Chairman Nam urged relevant agencies to map out the most possible appropriate compensation and clearance plans not later than 1 March so that the construction work can proceed on track.

Till date, the appraisal and approval has been completed for the construction of such major work segments as a raw water pumping station, and pipelines and some parts of the water treatment site, Mr Luong Thach Vy, the Head of the Management Board of the Da Nang Priority Infrastructure Investment Projects, the investor of the Hoa Lien Water Plant project, said.

The 1st stage of the project, which will include the building of a 13,606m2 reinforced concrete spillway on the Cu De River, and a 727m2 raw water pumping station with a daily capacity of 120,000m3 of water, is expected to be completed in June 2021.

1 c c3 a1c c4 91 c6 a1n v e1 bb 8b tri e1 bb 83n khai thi c c3 b4ng d e1 bb b1 c3 a1n nh c3 a0 m c3 a1y n c6 b0 e1 bb 9bc h c3 b2a li c3 aan


The Hoa Lien Water Plant progressing on track

Currently, the construction of drains, a sedimentation tank and fences, and the digging of foundations for the raw water pumping station and a management office, at the project are underway.

Also, 1.4m-diameter and 10.616km-long raw water pipelines will be placed underground running from the pumping station in Hoa Bac Commune’s Nam My Village to the water treatment plant in Hoa Lien Commune’s Quan Nam 1 Village.

Besides, mixing, reaction, sedimentation, filtration, storage, sludge compression and chlorine tanks, a polymer mixer, storage houses, warehouses, security houses, and a parking area will be created.

Once fully operational, the project will ensure the delivery of adequate water for homes and businesses in the districts of Lien Chieu, Thanh Khe, Hai Chau, Son Tra, and Hoa Vang.

With regard to the traffic improvement project at the western end of the Tran Thi Ly Bridge, 21.8% of the construction work has been completed till date.

Vice Chairman Nam asked the project’s contractors to speed up the construction progress in tandem with ensuring traffic safety nearby in the construction site.

1 b c3 a1o c c3 a1o ti e1 ba bfn c4 91 e1 bb 99 c c3 b4ng tr c3 acnh


Representatives of the management board of the traffic improvement project


at the western end of the Tran Thi Ly Bridge reporting on the construction progress

Covering an area of 131,521m2 in the wards of Hoa Cuong Bac and Hoa Thuan Dong, Hai Chau District, the traffic re-arrangement project borders Binh Minh 6 Street to the north, 29 March to the south, the Han River to the east, and military agencies and residential areas to the west.

As planned, the traffic project will consist of 3 levels. The lowest level will be a 4-lane road tunnel taking Duy Tan under the busy junctions with Le Dinh Tham and the western end of the Tran Thi Ly Bridge. The upper level on ground will be a roundabout, whilst the highest level will be a 14m-wide 4-lane steel overpass over 2 September Street. There will also be two 6m-wide frontage roads at the both sides of the overpass.

The project-affected infrastructure facilities and equipment owned by local government agencies and the city-based armed forces will be removed out of the construction sites in the coming time.


Source: Da Nang Today

TỔNG ĐÀI DỊCH VỤ CÔNG: (0236) 1022 hoặc *1022, miễn phí phục vụ  
1. Đường dây nóng tiếp nhận ý kiến phản ánh, góp ý của tổ chức, công dân.
2. Hướng dẫn, giải đáp quy định, chính sách, thông tin kinh tế – xã hội.
3. Hướng dẫn thực hiện thủ tục hành chính, dịch vụ công trực tuyến.
4. Cung cấp thông tin về hỗ trợ doanh nghiệp; quy định, chính sách hỗ trợ Khoa học công nghệ, đổi mới sáng tạo và chuyển đổi số.
5. Cung cấp thông tin về du lịch, sự kiện Văn hóa – Thể thao.
6. Cung cấp dịch vụ Tổng đài CSKH, nhắn tin CSKH, truyền thông, sự kiện và các dịch vụ tư vấn khác…

Để lại một bình luận

Email của bạn sẽ không được hiển thị công khai. Các trường bắt buộc được đánh dấu *